Login Nodes

◆ Operational

Recently, based on average data, it looks like this system has gone down for about 2475 minutes at a time.

21 entries, newest to oldest

September 2, 2026 at 08:30 UTC

Planned Grex outage - updating SLURM and home

Resolved after 6d 14h 40m of downtime
May 7, 2026 at 15:00 UTC

Unplanned Grex outage - restarting login nodes and OOD

Resolved after 1h 39m of downtime
April 29, 2026 at 17:00 UTC

Unplanned Grex outage - restarting login nodes and OOD

Resolved after 2h 0m
December 8, 2025 at 08:00 UTC

Planned Grex outage - updating storage

Resolved after 4h 0m of downtime
September 28, 2025 at 06:00 UTC

Grex login failure, login nodes and OOD.

Resolved after 1d 16h 0m
September 24, 2025 at 08:00 UTC

Planned Grex outage, updating storage and patching operating system

Resolved after 2d 9h 50m of downtime
April 23, 2025 at 09:10 UTC

Unplanned power outage in HPCC, Grex down

Resolved after 3h 30m of downtime
February 23, 2025 at 07:00 UTC

Planned HPCC datacentre power outage

Resolved after 1d 10h 10m of downtime
July 16, 2024 at 06:00 UTC

Planned HPCC/Grex outage for electrical and cooling work.

Resolved after 2d 12h 0m of downtime
May 7, 2024 at 09:00 UTC

Planned Grex outage for Lustre FS and Major Linux update

Resolved after 3d 4h 0m of downtime